* UPDATED Pre Christmas Delivery Time Frame *

If you require delivery prior to Christmas, please order ONLINE by Thursday 13th Dec by 12 noon.

Thank you for choosing Metal Roofing Online, we look forward to helping you with your roofing order. 

Image result for christmas tree cartoon

Select State:

Where are you shopping for today?

Delivery State:

Please note: item availability may change.
COLORBOND® Fascia Victoria ZINCALUME® Fascia Fascia Installation Diagram ZINCALUME®

Please select a state in the header.


Please select a state in the header.


COLOUR SELECTED:

This ZINCALUME® Steel Fascia System provides clean lines and is a smart alternative for all new homes.

Suits both tiled and metal roofs. 

May be integrated with most ZINCALUME® guttering profiles using our spring clip system which allows fast easy installation and adjustment to falls.


Delivery takes 3 - 4 working days.

Purchase ZINCALUME® FASCIA

 

Constructed from ZINCALUME® steel it will not contort, shrink or decay making it essentially maintenance free.

 

The fascia's may be integrated with most ZINCALUME® guttering profiles using our spring clip system which allows fast easy installation and adjustment to falls.

 

The Metal Fascia System has been designed for ease of use.  A spring clip snaps on to the Fascia and makes fixing of the gutters quick and easy. It is available in custom cut lengths to suit your application.

 

Suits both tiled and metal roofs

 

Custom cut to prevent waste, which gives extra savings

 

Designed to integrate perfectly with gutters


                      

 

PLEASE NOTE - MAXIMUM SUPPORT SPACING:


» Steel sheet roofing - 1200mm
» Tile roofing - 600mm




Fascia Installation Procedure:

Support Spacings:

The metal fascia should be supported on rafter clips at 1200mm (maximum centres). Do not use the fascia as an end span support.

 

Use at least two fixings (Hex Head screws; self drilling screw for steel, or Type 17 for timber) into the pre-punched holes & slots to secure to the rafter. If slots are used then further fixings may be recommended.

 

STEP 1

Fix a rafter clip at each end of the section, then run a string line from end to end. Attach one or two rafter brackets at mid region of the run, make sure these middle brackets are perfectly in line with the end ones.

 

STEP 2

Attached the fascia horizontally under each end clip, then flip the fascia forward and lever it over the top of the bracket into the vertical position.

 

STEP 3

Alter the fascia to the correct position by sliding it along the brackets, then secure the surplus of the intermediate brackets by twisting into fascia first, and then connecting to the rafters. (Notching, holing or distortion of the metal fascia is not recommended.)

 

STEP 4

When done correctly the fascia should be level around the hole house. Connect all corners and mitres, then the spring clips should be installed to create the fall for the gutter